Example Customer RequestA power developer is considering building a power plant in a large industrial area where there are modern steel mills. They developer asks, "Should we be concerned about the integrity of our generating units in that environment? Are there other system issues that we should study?" The objectives of the engagement are to identify and characterize system issues that may impact turbine-generator reliability and to perform screening level evaluations to determine if these issues may be dismissed, or warrant further detailed study. Work Scope1. Identify and characterize potential system issues (with interconnection utility):
2. Perform applicable screening studies of identified issues:
3. Issue report, including recommendations for detailed study if required Typical Data RequirementsSystem load, design and operating data via survey and interview with the interconnection utility. |
More About Equipment Application Consulting |